The hiring process at Southern Cooling Tower takes an average of 2 days when considering 1 user submitted interviews across all job titles. Candidates applying for Civil Engineering had the quickest hiring process (on average 2 days), whereas Civil Engineering roles had the slowest hiring process (on average 2 days).
I applied in-person. The process took 2 days. I interviewed at Southern Cooling Tower (Āsansol, West Bengal) in Apr 2012
Interview
their interview process was an sitter one. Although they recruited mainly mechanical engineer,Constrution was then primary focus. They were wanting mainly experienced in RCC cooling Plant experiences.Then they checked my c.v and some basic question. I had no experiences previous batching plant making. After some days they hired me as the project manager in Asansol-Burnpur IISCO plant.They asked me to join within one month.
Interview questions [2]
Question 1
Do you have any experiences in RCC structure construction?